Historical award

S. J. Thomas Co., Inc.

This record is historical buying context, not open work.

How current is this award history?

Fiscal year 2025: data through (14 days old).

Fiscal year 2026: data through (14 days old).

Official release availability details

Fiscal year 2025: This is the latest release listed by USAspending. A latest release can still omit recent activity.

Availability checked: .

Fiscal year 2026: This is the latest release listed by USAspending. A latest release can still omit recent activity.

Availability checked: .

Current award value
$1,915,079.32
Potential award value
$1,915,079.32
Total obligated to date
$1,915,079.32

Recorded work

THIS MOD IS TO INCORPORATE CLIN 0007 IN RESPONSE TO THE CONTRACTOR'S REQUEST FOR EQUITABLE ADJUSTMENT IN THE AMOUNT OF $31,438.72, AND EXTENDS THE SUBSTANTIAL COMPLETION DATE TO 10/31/24 FOR THE CHILLER REPLACEMENT PROJECT AT FOLEY BUILDING IN NY.

Award activity

Obligations in covered fiscal years
$31,438.72
Transactions in covered fiscal years
1

Award value and obligated funds describe different amounts. Review the official record for the full transaction history.

Record identifierCONT_AWD_47PC0221F0058_4740_47PC0220D0003_4740