Federal contractor · public award history
TETRA TECH, INC.
DBA TETRA TECH EM INC
Parent: TETRA TECH, INC. LMRMKLLL3LG5
- Awards we know about
- 30
- Typical size
- $539,685
- Middle of their public awards
- Dollars on those awards
- $60.87M
Most of their awards we can see fall roughly between $266,078 and $1.20M.
From official USAspending contract records — not a capability rating, past-performance score, or recommendation to team or bid.
Public award activity by year
Sum of award values in our USAspending index (not a full financial history).
- 2024$5.46M
- 2025$56.02M
Awarding agencies
- Environmental Protection Agency (29)
- Department of Transportation (1)
Industries & product codes
Award history
- Environmental Protection Agency$439,775
THE CONTRACTOR SHALL SUPPORT AGENCY OVERSITE OF REMOVAL SITE EVALUATIONS (RSES), INTERIM REMOVAL ACTIONS, WATER STUDIES, ENGINEERING EVALUATIONS AND COST ANALYSIS (EE/CAS), AND REMOVAL ACTIONS AT THE ABANDONED URANIUM MINES (AUMS) AND MINE AREAS NAME
- Environmental Protection Agency$266,078
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE FOR OVERSIGHT OF THE POTENTIALLY RESPONSIBLE PARTY (PRP) WESTERN NUCLEAR. AS THEY PERFORM ENGINEERING EVALUATIONS/COST ANALYSES (EE/CAS) AND REMOVAL ACTIONS (RAS) IN THE MARIANO LAKE AREA OF THE EASTE
- Environmental Protection Agency$3.62M
CONTRACTOR SHALL PROVIDE TECHNICAL DESIGN SERVICES FOR PLANNING & CONDUCTING CLEANUP VERIFICATION OF, TCRA, PILOT STUDIES, OR REQUIREMENTS AT TRONOX COVE TRANSFER STATION COMPLETE (CTS), ACCESS ROADS IN NN UNDER THE RAES 2 CONTRACT #68HE0923D0002
- Environmental Protection Agency$457,618
CONTRACTOR WILL ASSIST EPA IN COMMUNITY INVOLVEMENT OUTREACH SUPPORT INCLUDING CALLS, REMOTE MEETINGS AND FACE TO FACE ASSEMBLIES; WORK WILL ALSO INVOLVE RESEARCH FOR EPA.
- Environmental Protection Agency$205,630
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE FOR OPERATING UNMANNED AERIAL VEHICLES & SYSTEMS ON NAVAJO NATION IN ACCORDANCE WITH THE PROVISIONS OF THE EPA POLICY ON UAV/UAS UNDER THE RAES2 CONTRACT #68HE0923D0002 FOR EPA FOR REGIONS 6 &
- Environmental Protection Agency$359,073
TO 29 IS TO TO PROVIDE TECHNICAL ASSISTANCE FOR OVERSIGHT OF THE POTENTIALLY RESPONSIBLE PARTY (PRP) BNSF RAILWAY COMPANY (BNSF) AS THEY PERFORM A BACKGROUND STUDY, DATA GAPS ANALYSIS AND ENGINEERING EVALUATIONS/COST ANALYSES (EE/CA).
- Environmental Protection Agency$8.39M
THE CONTRACTOR PROVIDE TECHNICAL SUPPORT AND ASSISTANCE FOR THE USEPA NAVAJO ABANDONED URANIUM MINES (NAUM) PROGRAM AS IT DEVELOPS PROGRAM STANDARDS, TRAININGS AND WORKSHOPS, AND OTHER TECHNICAL SUPPORT WORK NEEDED FOR SITE INVESTIGATION.
- Environmental Protection Agency$74,833
THE CONTRACTOR SHALL SUPPORT DEVELOPMENT OF THE FEDERAL ACTIONS TO ADDRESS IMPACTS OF URANIUM CONTAMINATION IN THE NAVAJO NATION 2020-2029 (TEN-YEAR PLAN) UNDER THE RAES 2 CONTRACT #68HE0923D0002.
- Environmental Protection Agency$789,474
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE FOR OVERSIGHT OF THE POTENTIALLY RESPONSIBLE PARTY (PRP) EL PASO NATURAL GAS (EPNG) UNDER RAES 2 CONTRACT 68HE0923D0002.
- Environmental Protection Agency$539,685
THE PURPOSE OF THIS TASK ORDER IS TO PROVIDE TECHNICAL SUPPORT TO EPA REGION 6 IN FULFILLMENT OF ITS RESPONSIBILITIES FOR OVERSIGHT AND ENFORCEMENT OF ARCO'S ONGOING RI/FS UNDER THE ASAOC AND TO ASSIST EPA IN COORDINATION AND COMMUNICATION WITH
- Environmental Protection Agency$261,883
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE FOR OVERSIGHT OF THE POTENTIALLY RESPONSIBLE PARTY (PRP) CHEVRON U.S.A. INC. AS THEY FINALIZE AN ENGINEERING EVALUATIONS/COST ANALYSES (EE/CA) FOR THE MARIANO LAKE MINE IN THE EASTERN AGENCY OF THE NA
- Environmental Protection Agency$3.39M
THE CONTRACTOR SHALL PROVIDE SUPPORT FOR REMOVAL SITE EVALUATIONS (RSE) AT THE SKYLINE AUM WHICH ENCOMPASSES SKYLINE MINE AND UTAH NO. 1 LEASE IN OLJATO-MONUMENT VALLEY, UTAH UNDER THE NN-AUM RESPONSE ASSESSMENT AND EVALUATION SERVICES (RAES) II CONT
- Environmental Protection Agency$265,624
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE FOR OVERSIGHT OF THE POTENTIALLY RESPONSIBLE PARTY (PRP) HOMESTAKE MINING COMPANY (HOMESTAKE) AS THEY PERFORM AN ENGINEERING EVALUATIONS/COST ANALYSIS (EE/CA) FOR THE MAC & BLACK JACK MINES IN THE
- Environmental Protection Agency$1.07M
THE CONTRACTOR SHALL PERFORM TASKS REQUIRED TO PROVIDE TECHNICAL ASSISTANCE TO USEPA FOR DATA AND RECORDS MANAGEMENT RELATED TO THE NAVAJO AUM PROGRAM. THIS IS TASK ORDER 6 FOR THE RAES 2 CONTRACT, #68HE09D0002 FOR USEPA REGIONS 6 & 9.
- Environmental Protection Agency$1.20M
THE CONTRACTOR SHALL PROVIDE SUPPORT NEEDED FOR TIME-CRITICAL REMOVAL ACTION (TCRA) PLANNING AND OVERSIGHT SUPPORT ASSOCIATED WITH THE OLD CHURCH ROCK MINE SITE, AS WELL AS PLANNING AND SCOPING FOR A NON-TIME CRITICAL REMOVAL ACTION (NTCRA) ENGINEERI
- Environmental Protection Agency$287,658
THE CONTRACTOR SHALL PROVIDE SUPPORT NEEDED FOR NTCRA PLANNING AND OVERSIGHT SUPPORT ASSOCIATED WITH ABANDONED URANIUM MINE (AUM) ON BABBITT RANCHES UNDER RAES 2 CONTRACT #68HE0923D0002.
- Environmental Protection Agency$161,316
THE CONTRACTOR SHALL PROVIDE SUPPORT FOR NON TIME-CRITICAL REMOVAL ACTION PLANNING & OVERSIGHT SUPT ASSOCIATED W/ENPRO HOLDINGS ON NAVAJO NATION UNDER THE RESPONSE ASSESSMENT & EVALUATION SERVICES (RAES) II CONTRACT #68HE0923D0002.
- Environmental Protection Agency$582,364
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE TASKS TO SUPPORT AGENCY OVERSIGHT OF REMOVAL SITE EVALUATIONS (RSES), INTERIM REMOVAL ACTIONS, ENGINEERING EVALUATION AND COST ANALYSIS (EE/CA), AND ANY OTHER ACTIVITY AT THE ABANDONED URANIUM MINES (
- Environmental Protection Agency—
THE PURPOSE OF THIS IDIQ CONTRACT IS TO PROVIDE TECHNICAL ASSESSMENT SERVICES FOR THE ABANDONED URANIUM MINES ON AND AROUND THE NAVAJO NATION FOR REGIONS 6 & 9.
- Environmental Protection Agency$764,181
THE CONTRACTOR SHALL PROVIDE TECHNICAL ASSISTANCE TO USEPA FOR TECHNICAL ASSISTANCE TO THE CONTAMINATED STRUCTURES PROGRAM UNDER THE RAES 2 CONTRACT.
- Environmental Protection Agency$10.66M
THE CONTRACTOR SHALL PROVIDE THE SUPPORT NEEDED FOR TECHNICAL DESIGN SERVICES,& PLANNING AND CONDUCTING CLEANUP VERIFICATION OF TCRAS, PILOT STUDIES, OR OTHER INTERIM ACTIONS AT TRONOX AUMS UNDER THE RAES II CONTRACT #68HE0923D0002 FOR EPA FOR RE
- Environmental Protection Agency$685,955
THE PURPOSE OF THIS TASK ORDER IS ESTABLISH A TASK ORDER 27 TO PROVIDE TECHNICAL SUPPORT TO REGION 6 FOR OVERSIGHT OF AN ONGOING PRP RI/FS AND GOVERNMENT RI/FS AT THE HOMESTAKE MINING COMPANY UNDER THE RAES 2 CONTRACT.
- Environmental Protection Agency$6.10M
THE CONTRACTOR SHALL SUPPORT REQUIREMENTS FOR DEVELOPING A CONCEPTUAL SITE MODEL (CSM), A REMEDIAL INVESTIGATION (RI), A RISK ASSESSMENT (RA), AND A FEASIBILITY STUDY (FS), COLLECTIVELY REFERRED TO AS AN RI/FS, AT THE LUKACHUKAI MOUNTAINS MINING DIST
- Department of Transportation$169,064
ENVIRONMENTAL ASSESSMENT REPLACEMENT OF THE AIR ROUTE SURVEILLANCE RADAR (ARSR) ON MT. KA`ALA, OAHU, HAWAII
- Environmental Protection Agency$96,818
THE CONTRACTOR SHALL PERFORM OVERSITE AND TECHNICAL REVIEW FOR REMOVAL SITE EVALUATIONS (RSE) AND RISK ASSESSMENT DOCUMENTS FOR WELLS CARGO ABANDONED URANIUM MINES (AUMS) UNDER THE RAES 2 CONTRACT 68HE0923D0002.
- Environmental Protection Agency$14.28M
THE CONTRACTOR SHALL PERFORM REQUIRED TO CONDUCT THE ENGINEERING EVALUATION/COST ANALYSIS (EE/CA) AND RELATED TASKS AT THE FOLLOWING TRONOX ABANDONED URANIUM MINES LOCATED IN NAVAJO NATION'S NORTHERN AGENCY. THIS IS A TASK ORDER UNDER RAES 2 CON
- Environmental Protection Agency$529,309
THE CONTRACTOR SHALL PROVIDE EVALUATIONS FOR THE REMAINING KNOWN 278 UNFUNDED AUMS AND MINE AREAS ON THE NAVAJO NATION UNDER THE NN-AUM RESPONSE ASSESSMENT AND EVALUATION SERVICES (RAES) II CONTRACT FOR EPA FOR REGIONS 6 & 9.
- Environmental Protection Agency$385,687
THE CONTRACTOR SHALL PROVIDE SUPPORT REQUIRED FOR AGENCY OVERSIGHT OF THE UNITED NUCLEAR CORPORATION/GENERAL ELECTRIC (UNC/GE) WORK AT THE NORTHEAST CHURCH ROCK (NECR) MINE SITE UNDER RAES 2 CONTRACT.
- Environmental Protection Agency$787,071
CONTRACTOR WILL PERFORM ENGINEERING EVALUATION/COST ANALYSIS (EE/CA) AND RELATED TASKS AT THE SECTION 32/33 MINES FOR THE NAVAJO NATION AUM RESPONSE ASSESSMENT AND EVALUATION SERVICES (RAES) II CONTRACT FOR EPA FOR REGIONS 6 & 9.
- Environmental Protection Agency$4.67M
CONTRACTOR WILL PERFORM ENGINEERING EVALUATION/COST ANALYSIS (EE/CA) AND RELATED TASKS AT THE QUIVIRA MINE FOR THE RESPONSE ASSESSMENT AND EVALUATION SERVICES (RAES) II CONTRACT FOR EPA FOR REGIONS 6 & 9.