Multi -Roof Replacement Project
Energy, Department of · ENERGY, DEPARTMENT OF
This notice is not accepting responses (deadline was Feb 27, 2026, 4:00 PM EST).
Page kept for research and related open opportunities below. For current work in this category, use the related notices or browse hubs.
- Response deadline
- Feb 27, 2026, 4:00 PM EST
- Posted
- Jan 28, 2026
- Solicitation
- RFP26-021R
- Set-aside
- No Set aside used
- Place of performance
- Princeton, NJ, USA
- Contracting office
- PRINCETON LAB - DOE CONTRACTOR · Princeton · NJ
- Source
- SAM.gov · updated Jul 5, 2026
Description
There are several existing roofs (C50 ESAT Building/C52 PLT Power Building/C60 C Site Pump House/D45 Rad Waste Handling Facility) which are past their useful life requiring costly maintenance to upkeep. Severe water infiltration occurs regularly at failing joints, punctures, and flashing. Portions of existing metal coping have pulled away during storm events causing large sections of membrane to separate from the substrate. A catastrophic failure to one of these roofs would negatively impact the ability to conduct the top priority experimental operations in the Laboratory. 1.2. SCOPE 1.2.1. The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required replace the noted roofs and specified components per the associated contract documents. Construction scope includes the following: 1.2.1.1. Remove and replace existing built-up roofs at PPPL. Buildings include: 1.2.1.1.1. C50 � ESAT Building 1.2.1.1.2. C52 � PLT Power Building 1.2.1.1.3. C60 � C Site Pump House 1.2.1.1.4. D45 � Rad Waste Handling Facility 1.2.1.2. Demolition including removal of existing membrane, cover board, insulation, metal trim, flashing, coping and any other miscellaneous roofing material accessories. 1.2.1.3. Remove and recycle stone ballast on ballasted roofs. Recycle documentation to be provided to PPPL. 1.2.1.4. Additional integrated roof elements shall be inspected and replaced as specified within this SOW. Elements include: wood blocking, roof drains, gutters, scuppers, downspouts, and metal/concrete roof panels. 1.2.1.5. Abandoned equipment shall be removed to a point that does not affect new roof installation. Any equipment that should be temporarily relocated so roof replacement work can be completed shall be the responsibility of the roofing contractor. 1.2.1.6. Contractor to furnish and install 2 layers of 2.6� ISO. 1.2.1.7. Contractor to furnish and install �� HD coverboard mechanically fastened. 1.2.1.8. Contractor to furnish and install 145 mil Carlisle Fleeceback EPDM, black in color adhered to coverboard. 1.2.1.9. Contractor to furnish and install counter flashing and copings, expansion joints and other roofing components as required for manufacturer�s warranty. Page 3 of 21 1.2.1.10. The new roof system shall be comprised of the following materials: EPDM membrane, cover board, and insulation. 1.2.1.10.1. Meets a minimum insulating value of R-30 average. Modifications to the existing building envelope are required to accommodate additional insulation. 1.2.1.10.2. Flexible walkway pads shall be provided to all operating equipment/drain locations and as necessary to meet manufacturer�s requirements. 1.2.1.10.3. All materials shall be furnished by Carlisle Syntec Systems and shall meet all manufacturer specifications to obtain a minimum manufacturer system warranty of 30 years along with a 2-year installers warranty. The warranty coverage shall include incidental membrane punctures, damage from hail and a minimum of 72- mph peak gust wind speeds. 1.2.1.11. Roof perimeter guardrails shall be provided on all roofs. See attached guardrail cut sheet for details. 1.2.1.12. New and higher curbs as required due to the new roof installation work. 1.2.1.13. Contractor to build up existing roof vents as required due to the new roof work. 1.2.1.14. Expansion joint to be raised up to account for new roof insulation height for the ESAT building roof. 1.2.1.15. Contractor to add a new roof drain at the Northwest section of the ESAT building roof. 1.2.1.16. Contractor to replace all existing roof scuppers with new. 1.2.1.17. Contractor to replace all existing roof drains with new. 1.2.1.18. Contractor to provide minimum of 12� overlap between the existing adjacent roof membrane system and provide written confirmation the systems are compatible. 1.2.1.19. Contractor to temporary relocate and reinstall any fall protection anchor systems identified on roof sections. 1.2.1.20. Contractor to install secondary drainage per code in addition to existing drains for the PLT building roof. 1.2.1.21. If necessary, existing asbestos elements shall be mitigated by PPPL. Subcontractor to assist the abatement contractor to bring the sealed roofing material down from roof area to grade with lift equipment. Coordination of this work shall be completed in concert with all other construction activities. The subcontractor to follow directly after PPPL abatement contractor to install new roofing system. The construction subcontractor shall be responsible to coordinate all work with PPPL. 1.2.1.22. Any and all equipment that requires power disconnect has to be coordinated with PPPL a minimum of 72 hours prior. All equipment that will be out of service shall be minimized. 1.2.1.23. All roof fans and equipment are to be salvaged, protected, and reinstalled. THERE ARE (5) COVER LETTER SECTIONS TO THE RFP. THERE ARE FILES ATTACHED TO EACH COVER LETTER. TO VIEW THE ATTACHMENTS YOU MUST (1) FIRST DOWNLOAD EACH COVER LETTER SECTION TO YOUR DESKTOP. (2) AFTER DOWNLOADING EACH COVER LETTER--REOPENED EACH ONE (ON YOUR DESKTOP) YOU SHOULD BE ABLE TO SEE THE ATTACHED FILES ON THE RIGHT HAND SIDE OF THE COMPUTER SCREEN. BE SURE TO UTILIZE ADOBE ACROBAT SOFTWARE TO VIEW THE PDF FILES
What similar awards have paid
Real federal awards already on the books in a similar lane — so you can size the opportunity, not guess. This is public history, not a bid price, cost estimate, or prediction that you will win.
Typical award size
$220,063
Middle of the pack for similar past awards
Most similar awards fall between $88,594 and $881,276
Who has won work like this
Public awardees in this lane — useful for competitor scan or teaming ideas, not a ranked list of “best” firms.
- 1EPC SERVICE INC5 awards$11.55M
- 2BLUE PACIFIC JV LLC1 award$9.97M
- 3T1 CONSTRUCTION LLC1 award$8.18M
- 4PEM CONSTRUCTION, LLC1 award$6.65M
- 5K2 CONTRACTING GROUP, LLC1 award$4.92M
- 6HSU DEVELOPMENT, INC.6 awards$4.59M
- 7WHITING-TURNER CONTRACTING COMPANY, THE2 awards$4.45M
- 8THE CONSTRUCTION SERVICES GROUP INC1 award$4.42M
Drawn from official USAspending contract records in our index. Always confirm requirements on the SAM.gov notice before you bid.
Intelligence only — not legal advice or a guarantee of award. Always verify requirements on the official SAM.gov notice. Past award amounts are public history, not a suggested bid or prediction. Notice ID 8de1da092b6343039e06f3f23d7df974.