ClosedSolicitation
Veterans Affairs, Department of contract category

Y1DA--528A6-26-611 Abate Asbestos Pipe Insulation - B76

Veterans Affairs, Department of · VETERANS AFFAIRS, DEPARTMENT OF

This notice is not accepting responses (deadline was Dec 17, 2025, 12:30 PM EST).

Page kept for research and related open opportunities below. For current work in this category, use the related notices or browse hubs.

Response deadline
Dec 17, 2025, 12:30 PM EST
Posted
Dec 10, 2025
Solicitation
36C24226B0021
Set-aside
None listed
Place of performance
Contracting office
242-NETWORK CONTRACT OFFICE 02 (36C242) · ALBANY · NY
Source
SAM.gov · updated Jul 5, 2026

Description

Abate Asbestos Pipe Insulation � B76 528A6-26-611 GENERAL PROJECT WORK SCOPE DESCRIPTION Existing Conditions: The Bath VAMC is located at 76 Veterans Avenue, Bath, NY 14810. The layout is a campus with more than 30 buildings located on over 200 acres. Normal working hours are Monday � Friday 8:00am � 4:30pm. The Scope of this project includes but is not limited to the abatement of ACM pipe insulation found within Building 76. Contactor shall follow all requirements and procedures set by the local, state, and federal rule, regulation, and guidelines for the proper removal and disposal of ACM. Building 76 being a fully operational Medical Center may restrict the hours of work and may require off-tour work to ensure continuous operations of the facility as directed by the COR. Contractor shall have 30 days from the �Notice to Proceed� to complete all work. Scope of Work: 1. Demolition: a. Contractor is to provide all labor, material, equipment, supervision, to complete the removal of approximately 200 LF of ACM insulation found on existing plumbing from the crawl space and runs vertically through to the 2nd floor. Contractor is required to dispose of all ACM at an approved location offsite. Clear exposure/wall removal is to be completed by Medical Center maintenance shops prior to the start of the abatement. b. Part of scheduled abatement work is within basement/crawl space which is considered a confined space. 2. Safety Measures: a. Review and incorporate risk assessment and interim life safety plans and measures into safety and construction planning. i. Pre Construction Risk Analysis (PCRA) by VA ii. Interim Life Safety Measures (ILSM) by VA b. Generate and follow a safety plan and incorporate risk and life safety assessments. 3. Communication and Standards a. All contract direction, changes, financials, and contract performance are the responsibility of the VAMC Contracting Officer (CO). b. Contracting Officers Technical Representative (COR) is responsible for the day-today operations in project and the primary point of contact (POC) for the project. i. Communications to/from VAMC ii. Technical communications, submittals, RFI�s, change orders iii. On site visits for construction and sub-contractors iv. Construction coordination c. Project is required to use Autodesk Construction Cloud Build Platform (ACC) i. Bath VAMC will provide licensing, permissions, and online training for this cloud-based tool at no cost to the contractors. ii. Contractors are required to actively use Build on ACC for project documentation and coordination. iii. ACC is used for submittals, RFI�s, project communications and documentation. 1. No contract financial information on ACC. 2. No personal identification information on ACC. Code requirements: The installed product must, at a minimum, be in accordance with all applicable codes including Veterans Affairs standards which can be found at https://www.cfm.va.gov/til/. This will include, but not be limited to: Department of Veterans Affairs Design Manuals, VA Publications, and Construction Standards, National Fire Protection Code (NFPA), Life Safety Code, Underwriters Laboratory (UL), International Building Code IBC, National Electric Code (NEC), the VA Information Security Handbook 6500.6, Occupational Health and Safety (OSHA), and Environmental Protection Agency (EPA) requirements (to include Mold Remediation in Schools and Commercial Buildings). All work will be completed by certified individuals. Contract Drawings: Please see attached. Specifications: Please see attached. General Requirements: A. The contractor shall review the contract documents for conflicts. Where conflicts exist work shall not proceed until the COR has been notified and has given direction. B. Where incidental work is required to accomplish work shown on the drawings, this work is implied and shall be included as part of the base bid. C. Prior to any work commencing in an area, the contractor shall notify the COR of his intention to work in the area and shall schedule a walkthrough with the COR to determine existing conditions. D. After the work, the existing work areas shall be returned to their original state before final approval shall be given. After the completion of construction, the contractor shall completely clean all surfaces of construction debris. E. The contractor shall receive all deliveries of materials, equipment, tools, or other goods off station, and bring them to the job site. The Bath VA shall not accept deliveries for project purposes. F. The contractor shall prepare and submit an excel spreadsheet submittal log listing all submittals required. The worksheet shall be submitted by the contractor and reviewed and re-submitted as necessary. G. The contractor shall not proceed with any on-site work until the completion of the submittal process or approval to proceed from the CO and COR without completion of the submittal process. Not less than 14 calendar days shall be planned for COR review of each submittal. Resubmittals shall be provided as required by the COR, and shall be treated as a new, separate submittal. H. Any non-lead time materials will only be paid for when installed. I. Any items identified as punch list items will be fixed prior to project closeout. J. Special care will be taken to secure tools and construction equipment during construction as this facility has patients in it. K. Work cleanliness must be adhered to throughout the project. L. Sounds and vibrations must be kept to a minimum to avoid patient disruption. The COR reserves the right to stop work if sound and vibrations are impacting patient living or employees. M. Contractor staging area is east of railroad tracks, coordinate with COR. N. Off tour work may be required to minimize the impact on Veterans and employees. O. The contractor shall warranty all work including for 1 year from the date of acceptance. Warranty shall include any labor or parts necessary to ensure complete functionality of the new area. P. The contractor shall plan accordingly to stage and store materials in the contractor�s designated area shown. Q. The contractor shall be responsible for coordinating any traffic interruption with the COR. The contractor is responsible for providing interior pedestrian traffic control as well as any exterior traffic control personnel as needed during the period of the performance. Submittals: Submittals are required for all items outlined in the specification and include but are not limited to the submittals as shown in the submittal log. Project Duration: The total project duration for this project is not to exceed 30 days from the date of the NTP issuance. This includes all processes starting with submission and approval of all submittals and ending with final punch list c

What similar awards have paid

Real federal awards already on the books in a similar lane — so you can size the opportunity, not guess. This is public history, not a bid price, cost estimate, or prediction that you will win.

Typical award size

$233,278

Middle of the pack for similar past awards

Most similar awards fall between $38,750 and $1.33M

Lower end$38,750Typical$233,278Higher end$1.33M
Based on 500+ similar awardsSame industry code (562910)Prime contracts (not umbrella IDVs)

Who has won work like this

Public awardees in this lane — useful for competitor scan or teaming ideas, not a ranked list of “best” firms.

Drawn from official USAspending contract records in our index. Always confirm requirements on the SAM.gov notice before you bid.

Intelligence only — not legal advice or a guarantee of award. Always verify requirements on the official SAM.gov notice. Past award amounts are public history, not a suggested bid or prediction. Notice ID dc19584ae30149ebba21dcdde08b5a16.

Similar open government contracts

More in 562910 →
Construction

Pine Ridge Hospital Roof Replacement

HEALTH AND HUMAN SERVICES, DEPARTMENT OF · INDIAN HEALTH SERVICE

Presolicitation · Indian Small Business Economic Enterprise (ISBEE) Set-Aside (specific to Department of Interior and Indian Health Services) · NAICS 236220 · SD · Due Jul 16, 2026

Construction

Crownpoint Medical Gas Upgrade Construction

HEALTH AND HUMAN SERVICES, DEPARTMENT OF · INDIAN HEALTH SERVICE

Solicitation · Indian Small Business Economic Enterprise (ISBEE) Set-Aside (specific to Department of Interior and Indian Health Services) · NAICS 236220 · NM · Due Jul 16, 2026

Stephenson Taylor Water Line Extension

HEALTH AND HUMAN SERVICES, DEPARTMENT OF · INDIAN HEALTH SERVICE

Presolicitation · Indian Small Business Economic Enterprise (ISBEE) Set-Aside (specific to Department of Interior and Indian Health Services) · OK · Due Jul 19, 2026

Construction

Y1DA--Replace Air Handling Units in Building 42

VETERANS AFFAIRS, DEPARTMENT OF · VETERANS AFFAIRS, DEPARTMENT OF

Presolicitation · Service-Disabled Veteran-Owned Small Business Set Aside · NAICS 238220 · NC · Due Jul 20, 2026

Construction

Y1DA--NRM 630-24-105 Conduct Duct Bank Survey

VETERANS AFFAIRS, DEPARTMENT OF · VETERANS AFFAIRS, DEPARTMENT OF

Combined Synopsis/Solicitation · Service-Disabled Veteran-Owned Small Business Set Aside · NAICS 238210 · Due Jul 20, 2026

Construction

Y1DA--CON 668-21-100 Upgrade AHUs 18-20-22 Mechanical Systems

VETERANS AFFAIRS, DEPARTMENT OF · VETERANS AFFAIRS, DEPARTMENT OF

Solicitation · Service-Disabled Veteran-Owned Small Business Set Aside · NAICS 238220 · WA · Due Jul 21, 2026

Federal vendorsMore from Veterans Affairs, Department ofNAICS 562910PSC Y1DA