Military Construction Project (MILCON) P732 Design-Bid-Build, Electrical Distribution System Upgrades (Gosport Substation Only) at Norfolk Naval Shipyard (NNSY) in Portsmouth, Virginia.
Dept of Defense · DEPT OF THE NAVY
This notice is not accepting responses (deadline was Apr 2, 2026, 3:00 PM EDT).
Page kept for research and related open opportunities below. For current work in this category, use the related notices or browse hubs.
- Response deadline
- Apr 2, 2026, 3:00 PM EDT
- Posted
- Mar 5, 2026
- Solicitation
- N6247026R0015
- Set-aside
- No Set aside used
- Place of performance
- Portsmouth, VA, USA
- Contracting office
- NAVFACSYSCOM ATLANTIC · NORFOLK · VA
- Source
- SAM.gov · updated Jul 5, 2026
Description
READ THE ATTACHED SOLICITATION DOCUMENT IN ITS ENTIRETY. YOU WILL NEED TO REQUEST THE SPECIFICATIONS VIA EMAIL AND SEND ALL PPIs TO THE CONTRACT SPECIALIST LISTED BELOW: Daniel Rocha; daniel.r.rocha2.civ@us.navy.mil Military Construction Project (MILCON) P732 Design-Bid-Build, Electrical Distribution System Upgrades (Gosport Substation Only) at Norfolk Naval Shipyard (NNSY) in Portsmouth, Virginia. AMENDMENT 0001 1. Revise the Solicitation 2. Add Site Visit Information 3. Add Award Fee Information and Award Fee CLIN 4. Answer PPIs The Following Attachments were added: Attachment N - Award Fee Plan Attachment O - SECNAV 5512 Attachment P - BLANK DBIDS or VISITOR REQUEST Attachment Q - Approved Identity Proofing Documents Attachment R - Criteria for Denying Access to Navy Installations AMENDMENT 0002 1. Revise the Solicitation 2. Answer PPIs AMENDMENT 0003 1. Add revised Specification "01 30 00.00 22" attachment 2. Answer PPIs 3. Add Site Visit Sign-in Roster AMENDMENT 0004 1. Revise the solicitation 2. Remove Project Labor Agreement Requirement (PLA) 3. Extend the proposal due date to 18 March 2026 AMENDMENT 0005 1. Extend the proposal due date 2. Revise the solicitation section 00 70 00 - Conditions of the Contract 3. Answer PPIs 4. Revise Clause 52.211-12 Liquidated Damages-Construction. 5. Revise Clause 52.211-10 Commencement, Prosecution, and Completion of Work. 6. Revise Factor 3 - Schedule 7. Revise Attachment G - Price Proposal Form 8. Revise Specifications 9. Revise Drawings THE PPI PERIOD IS NOT EXTENDED WITH THE SOLICITATION DUE DATE.
What similar awards have paid
Real federal awards already on the books in a similar lane — so you can size the opportunity, not guess. This is public history, not a bid price, cost estimate, or prediction that you will win.
Typical award size
$2.02M
Middle of the pack for similar past awards
Most similar awards fall between $111,195 and $10.99M
Who has won work like this
Public awardees in this lane — useful for competitor scan or teaming ideas, not a ranked list of “best” firms.
- 1SCALFO ELECTRIC INC.1 award$24.22M
- 2TDX POWER SERVICES LLC1 award$16.36M
- 3BILLY W. JARRETT CONSTRUCTION COMPANY, INC.1 award$15.26M
- 4EAST COAST POWERLINE LLC1 award$15.06M
- 5CCI FACILITY CONTRACTORS, LLC1 award$14.51M
- 6TALION CONSTRUCTION, LLC1 award$12.23M
- 7SUNFLOW ENERGY CORP1 award$7.29M
- 8CHROME ELECTRIC, LLC1 award$6.64M
Drawn from official USAspending contract records in our index. Always confirm requirements on the SAM.gov notice before you bid.